By Tom Noreen
Just as work on White Creek Avenue finishes up, Michigan Paving and Materials will begin milling Northland Drive starting at South Street on June 12. A week later, Dean’s Excavating will start removing concrete and begin widening the roadbed to three lanes. Phase 1 work will continue south to 16 Mile Road.
Reconstruction of the 16 Mile intersection will complete Phase 2.This intersection may be closed for up to a week. Phases 1 and 2 are slated for completion in mid August. Phase 3 will include widening the bridge over Little Cedar Creek.
The projected date of completion is September 25.